Recommendations
01 January 2012
Closed2016-004:
Investigation into SPADs on the IÉ network from January 2012 to July 2015
Iarnród Éireann (Railway Undertaking) should commission an independent review, in terms of human …
01 January 2012
Closed2016-003:
Investigation into SPADs on the IÉ network from January 2012 to July 2015
Iarnród Éireann (Infrastructure Manager) should review the functionality of signals in the …
01 January 2012
Open / In progress2016-002:
Investigation into SPADs on the IÉ network from January 2012 to July 2015
Iarnród Éireann (Infrastructure Manager) should review the functionality of the Automatic Train …
01 January 2012
Open / In progress2016-001:
Investigation into SPADs on the IÉ network from January 2012 to July 2015
Iarnród Éireann (IÉ) (Infrastructure Manager) must introduce an adequate train protection …
08 June 2014
Closed2015-004:
Car strikes train at level crossing XM250, Knockaphunta, Co Mayo.
The RSC, RSA and IÉ in consultation with any relevant stakeholders should agree a common policy in …
12 February 2014
Closed2015-003:
Vehicle struck by train at Corraun level crossing, XX024, Co. Mayo.
IÉ should ensure that where a Decision Line is present at a level crossing, that the purpose of …
12 February 2014
Further Evidence Requested2015-002:
Vehicle struck by train at Corraun level crossing, XX024, Co. Mayo.
IÉ should carry out a full review of known misused user worked level crossings on public and …
12 February 2014
Closed2015-001:
Vehicle struck by train at Corraun level crossing, XX024, Co. Mayo.
IÉ should consider options to upgrade the crossing to minimise direct action by the users.
07 November 2013
Open / In progress2014-028:
Tram fire on approach to Busáras Luas Stop.
Transdev should undertake a review of higher ignition temperature hydraulic oils to identify if …
31 December 2013
Closed2014-027:
Rock fall at Plunkett Station, Waterford.
IÉ IM CCE should review its Competence Management System in terms of both: its identification and …
31 December 2013
Closed2014-026:
Rock fall at Plunkett Station, Waterford.
IÉ IM CCE should fully adopt the compliance verification process and ensure the process includes …
31 December 2013
Closed2014-025:
Rock fall at Plunkett Station, Waterford.
IÉ IM CCE should complete thorough reviews of CCE-STR-STD-2100 and CCE-STR-GDN-2802 in terms of …