Recommendations
02 November 2020
Open / In progress202106-05:
Luas Overhead Line Failure, Stillorgan, 2nd November 2020
Transdev should investigate the reason for the build-up of Cupric Oxide on the Overhead Contact …
02 November 2020
Open / In progress202106-04:
Luas Overhead Line Failure, Stillorgan, 2nd November 2020
Transdev should include the electrical resistance measuring of vehicle earth bonding in the planned …
02 November 2020
Closed202106-03:
Luas Overhead Line Failure, Stillorgan, 2nd November 2020
Transdev should put a process in place that all trams involved in serious incidents have the On …
02 November 2020
Further Evidence Requested202106-02:
Luas Overhead Line Failure, Stillorgan, 2nd November 2020
Transdev should conduct a full review and update of their dewirement/incident management documents, …
02 November 2020
Closed202106-01:
Luas Overhead Line Failure, Stillorgan, 2nd November 2020
Transdev, along with S2M, should conduct a full review of their inspection processes for Overhead …
01 October 2020
Closed202105-07:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking (IÉ-RU) Chief Mechanical Engineer's Department to review and …
01 October 2020
Closed202105-06:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking Chief Mechanical Engineer's Department to include …
01 October 2020
Open / In progress202105-05:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Infrastructure Manager, Signalling, Electrical and Telecommunications (SET) …
01 October 2020
Closed202105-04:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking, Chief Mechanical Enginner's Department to include …
01 October 2020
Closed202105-03:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking and Iarnród Éireann Infrastructure Manager should review …
01 October 2020
Closed202105-02:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking (IÉ-RU), Chief Mechanical Engineer's Department should carry …
01 October 2020
Further Evidence Requested202105-01:
Overhead Line detachment, Pearse Station, 1st October 2020
Iarnród Éireann Railway Undertaking, Chief Mechanical Engineer's Department should in conjunction …
Showing 97 - 108 of 333